NASA to Take Corrective Action in Spacesuit Contract Protest

NASA has concluded that corrective action is appropriate in the Government Accountability Office (GAO) bid protest of Exploration Systems & Technology, Inc. NASA determined that
a compliance issue requires the termination of the contract for the Constellation Space Suit System with Oceaneering International, Inc. of Houston for the convenience of the government.

NASA anticipates that corrective action will involve reconsideration of its procurement decision. The pending protest litigation is subject to a Government Accountability Office protective order, NASA says.

NASA had awarded the contract on June 12. The spacesuit will protect astronauts during Constellation Program voyages to the International Space Station and, by 2020, the surface of the moon. The Constellation Space Suit System contract is for design, development, test, evaluation and production of equipment to support astronauts aboard the Orion crew exploration vehicle, the Altair lunar lander, and during human exploration of the
surface of the moon.

Suits and support systems will be needed for as many as four astronauts on moon voyages and as many as six space station travelers. For short trips to the moon, the suit design will support a week's worth of moon walks. The system also must be designed to support a significant number of moon walks during potential six-month lunar outpost expeditions. In addition, the
spacesuit and support systems will provide contingency spacewalk capability and protection against the launch and landing environment, such as spacecraft cabin leaks, NASA says.

Watch more breaking news now on our video feed:



Bookmark http://universeeverything.blogspot.com/ and drop back in sometime.

Labels: , , , ,

Monday, July 30, 2007

DOD Could Improve Pandemic Flu Preparedness, Audit Finds

An influenza pandemic could impair the military’s readiness, jeopardize ongoing military operations abroad, and threaten the day-to-day functioning of the Department of Defense (DOD) due to a large percentage of sick or absent personnel, according to a recent federal report.

Each of DOD’s nine combatant commands (COCOMs) has established or intends to establish a working group to prepare for an influenza pandemic, the Government Accountability Office (GAO) finds in a recent report. GAO is the nonpartisan investigative arm of Congress.

Additionally, eight of the nine COCOMs have developed or are developing a pandemic influenza plan. Half of the COCOMs have conducted exercises to test their pandemic influenza plans and several are taking steps to address lessons learned. Five of the nine COCOMs have started to use various media, training programs, and outreach events to inform their personnel about pandemic influenza. Each of the geographic COCOMs has worked or plans to work with nations in its area of responsibility to raise awareness about and assess capabilities for responding to avian and pandemic influenza, according to the GAO study.

GAO recommends that DOD take steps to clarify the COCOMs’ roles and responsibilities for pandemic influenza-related efforts, identify the sources and types of resources needed for the COCOMs to accomplish these efforts, and develop options to mitigate the effects of factors that are outside of their control. DOD concurred with each of these recommendations, GAO says.